    This video explains why every single engineering project ever has gone over the initial budget.

    https://www.youtube.com/watch?v=dOe_6vuaR_s

    When you factor in that a nuclear project will face additional hurdles, you get an idea why every reactor build these days is over budget.

    Because that initial budget was the back of the napkin calculation before any site surveys or permitting or anything else, because in order to get the permits for those site surveys and such, you need an initial budget.

    The press then reports these napkin numbers as if they were the final budget.

    As another note here, nuclear projects tend to face massive regulatory sabotage from people who are ideologically opposed for various reasons. (usually tracing back to money from fossil fuels). This drives up the cost considerably as well.

    • Sir_Osis_of_Liver@kbin.social
      link
      fedilink
      arrow-up
      0
      arrow-down
      1
      ·
      1 year ago

      I’ve spent 25 years in thermal generation, including some work on nukes, and there are a lot of issues with that video.

      Professional estimators are generally pretty accurate when it comes to thermal plants. A class D estimate would be ±20%, Class A ±5%. The problem arises when they have to spin unrealistic numbers in order to be competitive with other technologies. That’s when you get things that are off by 200% of the estimate.

      Speaking of which, over the history of the industry, the average nuclear reactor in the US is 207% of the initial estimate. That number has actually gotten worse going from 1st to 2nd to 3rd generation reactors, even though the reactors were simplified to reduce things like the number of pipe runs and control valves, etc, and the use of large pre-manufactured sub-assemblies. In order to become economic, reactor sizes have increased, which increases overall efficiency, the theory being an incremental increase in cost would be offset by the higher output. The trouble was, the increase in costs never ended up being anywhere close to ‘incremental’.

      Initial design costs and regulatory approval & fees typically should be in the range of 10-15% of capital costs. For the most part, that’s about where they land in practice. The bulk of the costs and cost overruns remain in construction, construction-management, material, and project financing, especially now that interest rates are increasing.

      The regulatory sabotage theory is BS. The French have been the largest nuclear industry proponents since their big construction boom in the 1970/80s. Yet their plants are just as likely to go over budget as anywhere else. The regulations are written based on accident/incidents in the past. They’re there for a reason.

      • chaogomu@kbin.social
        link
        fedilink
        arrow-up
        1
        ·
        1 year ago

        The regulatory sabotage is real.

        Here’s a link explaining it.

        https://rootsofprogress.org/devanney-on-the-nuclear-flop

        Do note that one of the major “safety” regulations, the one mandating a shutoff method to deal with a double ended guillotine break, is completely pointless, because a double ended guillotine break is actually impossible. Pipes don’t break like that. The more reliable safety standard is Leak Before Break, and yet, nuclear designers are actually forbidden from designing around that scenario because it would often interfere with the imaginary guillotine break.

        Then there are bans on multiplexing control wires. There are dozens of other random regulations that make nuclear plants slightly less safe, but extremely expensive.

        That doesn’t even touch on the permitting process. here’s a quote;

        the NRC does not benefit when power plants come online. Their budget does not increase proportional to gigawatts generated. Instead, the nuclear companies themselves pay the NRC for the time they spend reviewing applications, at something close to $300 an hour. This creates a perverse incentive: the more overhead, the more delays, the more revenue for the agency.

        The result: the NRC approval process now takes several years and costs literally hundreds of millions of dollars.